20130306201015dnx
Construction works
Country: Built (year): Output (kw):
IT New 750
Head (m): Capacity (m3/s): Completation (year):
5.6 14 2011 - 2013
Construction works
Bank protection
Construction of powerhouse
Construction works
Construction works
Construction works
Construction works powerhouse
River Esino weir

Genga

Project review

This SHPP is located in Genga town (comune of province of Ancona) in the Italian region of the Marche. This SHPP of derivation type is using hydro potential of the existing weir structure on the river Esino with the total output 750 kW.

The exploited river Esino is one of the major rivers of the Marche Region, interested along its course by many other hydropower plants, built since the first half of twentieth century both by national energy utilities and local private or public entities.

The turbines are horizontal tubular double regulated S-Kaplan type. SHPP Genga will be fully automated and remote-operated. This SHPP includes complete reconstruction of the existing weir and construction of the new hydropower plant.

Provided services

As general contrator Hydropol provides the site complex development, preparation of relevant studies, permitting, project design & engineering services and complete EPC delivery.