View of powerhouse
Country: Built (year): Output (kw):
RO 1916 650
Head (m): Capacity (m3/s): Completation (year):
34.6 2.3 2011 - 2013
View of powerhouse
Demolition works inside powerhouse
Disassembly of turbine
Intake

Breazova

Project review

This SHPP is a part of hydroenergetic cascade system in county Caras Severin near city Reşita in Western Romania.

Owner and investor of this project is CEZ Group which has bought this cascade system by acquisition of 100% share in company TMK Hydroenergy Power SRL.

Complete refurbishment of SHPP technology - installation of new turbine, generator, governor and another auxiliary equipment. Complete renewal of HV and LV electrical part. Civil works are in scope needed for new technology installation.

Provided services

As the general contractor, Hydropol is responsible for preparation of study, project design & engineering services and complete EPC delivery of the SHPP cascade modernization.